# Cost Estimate Level of Accuracy

Learn how cost estimate level of accuracy works, what the estimate accuracy range means, and how estimate classes and contingency fit into project cost estimating.

The cost estimate level of accuracy describes how close a project cost estimate is expected to land to the actual final cost, expressed as a range rather than a single number. It tells a reader how much trust to place in a figure before more design and pricing detail is available. This page explains the estimate accuracy range, the role of estimate classes, and how contingency covers the gap. 

## What the accuracy range expresses 

An estimate accuracy range shows the spread between a low and a high outcome around the stated project cost. Early figures sit in a wide band because scope and pricing are still open. As design detail and supplier quotes arrive, the band narrows and the estimate becomes more dependable. The range depends on how much of the work has been defined and priced, not on the size of the project alone. 

## Estimate classes and their detail 

Estimate classes group cost estimates by the amount of project definition behind them. An order of magnitude estimate relies on rough capacity or floor area figures and carries a wide band. A definitive estimate is built from detailed quantities, firm quotes and completed design, so its band is narrow. Moving from one class to the next requires real engineering and pricing work, not just a tighter number. 

## Contingency inside the range 

Contingency is the money set aside inside the estimate for known risks and minor scope that is not yet priced. It belongs inside the accuracy range and is not a substitute for good estimating. A wide band needs more contingency because more of the cost is still uncertain. Reviewing contingency at each estimate class keeps the allowance matched to the real level of definition. 

## Questions about cost estimate accuracy 

### What does cost estimate level of accuracy mean? 

The cost estimate level of accuracy is the expected spread between the estimated project cost and the final cost. It is shown as a range, such as a low and high figure around the base estimate. A wider range means less of the project has been defined and priced. The range tightens only when design and supplier pricing improve. 

### How is the estimate accuracy range set? 

The estimate accuracy range is set by the amount of project definition and priced information behind the figure. Rough capacity-based numbers give a wide range, while detailed quantities and firm quotes give a narrow one. The estimator records the range with the estimate so readers know its reliability. Class guidelines link each level of definition to a typical range. 

### What is the difference between an order of magnitude and a definitive estimate? 

An order of magnitude estimate uses rough parameters and carries a wide accuracy band. A definitive estimate is built from completed design, detailed quantities and firm supplier quotes. The definitive figure costs more to prepare but supports firm budget decisions. The two sit at opposite ends of the estimate classes. 

### How does contingency relate to estimate accuracy? 

Contingency is the allowance held inside the estimate for known risks and unpriced scope. It sits within the accuracy range and grows when the estimate class is early and the band is wide. Reviewing contingency as definition improves keeps the allowance honest. Contingency never replaces the work of tightening the estimate itself.